HOW WE WORK
The same operating standard sits behind every request, from a single power cycle to a data center move. It is the reason the closure report can be trusted.
The acceptance rule. If something unexpected turns up on site, we stop and call before expanding the change. Extra time is billed only after you approve it.
WHEN THINGS DON’T GO TO PLAN
AN EXAMPLE JOB
The on-site times match our sample closure report.
| When | What happens |
|---|---|
| Mon 09:10 | You send the request: a failed drive in bay 3, rack B-14, Skawina. The replacement ships to the site. |
| Mon 11:30 | You get the written quote: scope, window, fixed price, and the escort fee at cost. |
| Mon afternoon | You approve, and add the named engineer to the facility’s access list. |
| Tue 06:52 | Arrival at the facility; access and escort checked. |
| Tue 07:12 | Asset confirmed by serial and label before anything is touched. |
| Tue 07:21–07:26 | Drive replaced; your engineer confirms the RAID rebuild has started. |
| Tue 07:48 | Work done, the failed drive sealed in a numbered bag, site left. |
| Tue, same day | The closure report arrives: timeline, tests, serials, photos and custody. |
| After acceptance | You accept the report, or two business days pass without objection, and we invoice. |
CLOSURE REPORTS
Every visit ends with a closure report the same day; audit reports follow within two business days. It is how you know the work was done, and how your auditor, your client or your vendor knows it too.
Failed drives are logged by serial, sealed in a numbered bag and kept on site until handed to you or your partner, with a signed transfer. When drives are destroyed, the partner’s per-serial certificate is added to the report.
The report is accepted when you confirm it, or when there is no objection within two business days. Only then do we invoice the job.
COVERAGE
The core zone is Kraków and the Skawina data center cluster. We plan visits further out, and take work beyond that by arrangement.
The form asks for these. If you don’t know some of them yet, send what you have and we’ll ask.
Ready to send before any site access:
Describe the task, the site and the window. Written scope and price within four business hours.